Partidas adicionales como obra extraordinaria en un contrato de valor fijo Comentario a la sentencia de la Corte Suprema (Tercera Sala), de 7 de junio de 2017
Construction-works that are not estimated or valued in the accepted offer of a public tendering process are not included in a lump-sum contract price, and constitute extra works. A lump-sum price construction contract does not include works that both the tenderer and the successful bidder (the contr...
Gorde:
Egile nagusia: | |
---|---|
Formatua: | Artikulua |
Hizkuntza: | Gaztelania |
Argitaratua: |
2018
|
Gaiak: | |
Sarrera elektronikoa: | https://dialnet.unirioja.es/servlet/oaiart?codigo=7175025 |
Baliabidea: | Revista Jurídica Digital UANDES, ISSN 0719-7942, Vol. 2, Nº. 2, 2018, pags. 115-122 |